The project consisted of revamping the entire site in terms of the following works:
- decommissioning of the lines dedicated to the production of frozen products and expansion of the production capacity of the lines dedicated to the production of frozen pizzas;
- upgrading of the raw material warehouse, unloading area and production areas to accommodate the new production lines;
- functional upgrading of the existing storage cells to provide for the construction of the new packaging area;
- the construction of new facilities, including the pizza topping areas, a pre-loading cell with three refrigerated bays, the packaging warehouse, and technical support departments.